The nine probability inputs (P1 through P9) are structured legal judgements expressed as numbers. They are not statistical frequencies drawn from a large dataset of identical cases. There is no such dataset — there is only one Harrison v Aegon. What the numbers represent is this: if a competent legal analyst were to assess the probability that a court, having heard all the evidence, would find for the plaintiff on a specific discrete legal issue — that assessment, made explicit, documented, and calibrated against empirical anchor cases, is the input.
The justification for each number has four components, which are combined using a documented methodology:
What 18% residual probability against (e.g. on P3 at 82%) does not mean is that the plaintiff's lawyers are 18% likely to have the law wrong. It means: 18% allowance for judicial discretion, unexpected evidentiary rulings, cross-examination outcomes, arguments not yet anticipated, and the inherent unpredictability of any contested proceeding. The number is not a prediction. It is a calibrated, documented, stress-testable planning tool.
The consequence: any variation from a default value is a deliberate departure from the calibrated position. It requires a specific legal reason — new evidence, a counsel assessment, a material change in the defendant's position — not a preference for a better-looking output.
P1b (Jul 2006 / Oct 2008 Allens): A fictional LGI-TIMAP Agreement governs commissions — this agreement does not exist. Cited twice by Allens over 27 months. Never produced.
P2 (Jul 2021 inadvertent): Marketing Agreement was the actual basis — contradicted by the finance manager's own Excel formula disclosure (CC-5).
P2.5 (Aug 2024 Hallal — SMOKING GUN): "Marketing Agreement only relates to Australia — not Korea." This single admission destroys 19 years of justifications simultaneously. Every Korea calculation from 2005 was therefore unauthorised on Aegon's own concession.
P3 (Oct 2024 Hallal): Marketing Agreement irrelevant — MOC confers unilateral authority. This violates EA Clause 20 and was abandoned in 2003 when Harrison explicitly refused the rate reduction and Aegon accepted that refusal as decisive (CC-24).
CC-6 (Oct 2021) and CC-7 (Dec 2021): Progressive retraction of the cessation date (late 2007 → October 2007 → July 2005), each retraction an implicit acknowledgment the prior stated date was false — direct evidence of concealment.
CC-8 (Feb 2022) and CC-9 (Mar 2022): Aegon admits it cannot retrieve the basis or documentation for its estimation rates. A party that cannot document the basis of its calculation methodology cannot defend that methodology as contractually authorised.
$3,319,108 corrective payment (Feb/Mar 2024): Paid expressly as acknowledgment of "material accounting irregularities." You cannot make a corrective payment without implicitly admitting the prior calculation was wrong. The payment is an admission that cannot be walked back.
Pillar 2 — Active misdirection through eight contradictory explanations (KNOW→UNKNOW→KNOW sequence): Aegon knew the correct calculation (Two Sets of Books), claimed not to know the basis (CC-8/CC-9), then made admissions confirming it had always known (D3.70). The KNOW→UNKNOW→KNOW pattern is direct evidence of conscious concealment.
Pillar 3 — NDA weaponisation: Audit NDAs imposed at each verification attempt containing (a) mandatory destruction clauses, (b) conditions requiring Harrison to surrender fraud claims, and (c) penalty provisions deterring challenge to Aegon's disclosed figures. Clause 6.7(f) of the EA contains no provision permitting NDA conditions as a precondition to verification — the NDA conditions were therefore themselves a breach of the verification obligation and a tool of concealment.
Pillar 4 — Document destruction: D3.05 admission of document destruction after request.
Pillar 5 — 24-hour premeditation: D3.70 (2 August 2024) proves the suppression was deliberate and planned — "actuals were available at Reinsurer level... not made available to commission team." Deliberate suppression by senior management.
Limb 2 (demand accrual sequencing): The Deed cause of action did not accrue until the November 2025 demand. A right that had not yet accrued cannot be extinguished by s.63. Wardley Australia sequencing confirms this.
Limb 3 (s.54 acknowledgment): The February 2024 corrective payment constitutes a s.54 acknowledgment that independently resets the limitation clock for any remaining Deed obligation. Even on the most hostile limitation reading, s.54 protects the Deed claim.
Illegal NDA conditions: Three conditions attached to audit access that had no contractual basis and amounted to a demand that Harrison surrender fraud claims and consent to evidence destruction as a precondition to seeing his own commission data.
Five irreconcilable positions over 19 years: The sequential advancement and abandonment of five mutually inconsistent justifications for the Korea rate reduction, each requiring the court to conclude that the previous position was wrong, is the kind of conduct that attracts indemnity costs awards in NSW courts.
Continued denial after the Hallal admission: The August 2024 Hallal admission that the Marketing Agreement did not apply to Korea — which destroyed 19 years of prior justifications — did not produce any concession or settlement offer until April 2025, and then only a partial concession. Continued denial after a conclusive admission warrants indemnity costs.
Corrective payment without concession: The $3,319,108 corrective payment was made without any accompanying admission of liability — a tactical manoeuvre that required Harrison to continue litigation to establish what Aegon had already impliedly admitted by paying.